Skip to main content

Latest News

  1. Home
  2. News
  3. Lateral Isolation Valve Replac...
June, 2022
News

Lateral Isolation Valve Replacement (LIVR) Project – June 23, 2022

The District is in the process of a major rehabilitation project named the Lateral Isolation Valve Replacement (LIVR). The project involves the replacement of main shut off valves at each of the turn outs off the South Coast Conduit. This Thursday, June 23rd, the valves located at Lateral 2 will be replaced.

Customers will have water but may notice a drop in pressure during peak times of the day as the system will be re-routed. See map below of affected area or click here to view larger map.

The project is planned to take place from 8:00 am -5:00 pm on Thursday, June 23, 2022.

If you have any questions please feel free to contact, District Engineer, Brian King by email or phone at 805-684-2816×107.